Concrete Rebar Calculator

Bar counts, weight, and the half of the takeoff the other calculators leave out: cover, chairs and tie wire

← Back to the calculator
24 ft × 20 ft slab, #4 at 12 in o.c., 3/4 in cover → 24 + 20 bars, 970.5 ft, 648.3 lb net.

Then the part that gets forgotten: that 3/4 in cover demands a 1 in chair, the slab needs 42 chairs on a 4 ft support grid, and 480 intersections eat about 3.66 lb of tie wire. Order weight is 882 lb on 30 ft stock, not the 648.3 lb net — the difference is the offcut.

Open the calculator for your own dimensions, or read the three steps below.

What "concrete rebar calculator" usually means

Most tools under this word do the same first half: enter a slab, get bars and weight. That half is geometry, and it is solved. The second half is the accessories — and it is where the money and the callbacks are. Get the cover wrong and the inspection fails; forget the chairs and the top mat sinks into the slab during the pour; skip the tie wire and the crew stops work to go get a roll.

This page does the whole takeoff in three steps and shows every number, so you can check it against your own drawings.

Step 1 — the grid: bars, length and net weight

Work in clear distances, not overall dimensions. The first bar sits one cover in from the edge, so the usable span in each direction is the slab dimension less two covers. Convert to inches, and:

bars = floor( usable span (in) ÷ spacing (in) ) + 1 net length = (bars across × span along) + (bars along × span across)

For a 24 ft × 20 ft slab with #4 at 12 in on centre and 3/4 in cover:

usable span, 24 ft direction = 288 − 2 × 0.75 = 286.5 in usable span, 20 ft direction = 240 − 2 × 0.75 = 238.5 in bars across the 24 ft direction = floor(286.5 ÷ 12) + 1 = 23 + 1 = 24 bars across the 20 ft direction = floor(238.5 ÷ 12) + 1 = 19 + 1 = 20 net length = (24 × 23.875) + (20 × 19.875) = 573.0 + 397.5 = 970.5 ft net weight = 970.5 ft × 0.668 lb/ft = 648.3 lb of #4

0.668 lb/ft is the nominal unit weight of a #4 bar. The same number is on the size chart for every bar, and the weight calculator carries it through to order weight.

Step 2 — clear cover is not a choice, it is a table lookup

Here is the step no simple calculator shows. A bar needs concrete around it to bond, so cover has to be at least what the exposure demands, and that number is not a preference: it is ACI 318-19. Get it wrong in either direction and the slab is wrong — thin cover lets the bar corrode, thick cover costs chair height and eats the usable depth.

ConditionBar sizeMin. cover
Cast against & permanently in contact with earthAll3 in
Exposed to weather or soil#6 to #182 in
Exposed to weather or soil#5 and smaller1 1/2 in
Interior, beams & columnsAll1 1/2 in
Interior, slabs & walls#11 and smaller3/4 in

Swipe the table sideways for more columns →

The reinforcement sits inside the cover, on chairs. On a slab on grade the bottom mat is held up by chairs of a given height, and the chair height is what the drawings specify: the clear cover plus half a bar diameter. Buy the wrong chair and the cover is wrong, and the inspector sees it immediately.

ConditionCoverChair for #4Chair for #5Chair for #6Chair for #8
Earth contact (footing)3 in3 1/4 in3 5/16 in3 3/8 in3 1/2 in
Weather / soil, #6+2 in2 1/4 in2 5/16 in2 3/8 in2 1/2 in
Weather / soil, #5−1 1/2 in1 3/4 in1 13/16 in1 7/8 in2 in
Interior beam / column1 1/2 in1 3/4 in1 13/16 in1 7/8 in2 in
Interior slab / wall3/4 in1 in1 1/16 in1 1/8 in1 1/4 in

Swipe the table sideways for more columns →

Chair height = clear cover + one half the bar diameter. Values rounded to the nearest 1/16 in; chairs are sold in 1/8 in and 1/4 in steps, so round up.

Section through a slab on grade: the chair height sets the clear cover, and the cover is a dimension the code fixes One slab section, three numbers the chair height sets the cover; the cover is a code dimension, not a preference concrete chairs ↩ hold the top mat bar spacing runs in here cover = 3/4 in interior slab / 3 in earth contact chair grid: 3 ft to 4 ft each way bottom mat (chairs) top mat (chairs / bolsters)
The chair is not a convenience, it is the mechanism that holds the cover the code requires. Set the chair height from the table above, count one chair per support-grid cell, and the cover on the drawing and the cover in the slab are the same number.

Step 3 — the accessories: chairs and tie wire

Once you know the intersections and the slab area, the accessories are arithmetic.

Chairs

chairs = ( floor( length ÷ grid ) + 1 ) × ( floor( width ÷ grid ) + 1 ) = ( floor( 24 ÷ 4 ) + 1 ) × ( floor( 20 ÷ 4 ) + 1 ) = 7 × 6 = 42 chairs (4 ft support grid) the same slab on a 3 ft grid: = ( floor( 24 ÷ 3 ) + 1 ) × ( floor( 20 ÷ 3 ) + 1 ) = 9 × 7 = 63 chairs

Count grid points, not area. The shortcut of one chair per 4 sq ft gives 480 ÷ 4 = 120 chairs on this slab, nearly three times the 42 you will place, because one chair supports a patch of mat rather than a single point. Tighten the support grid from 4 ft to 3 ft and the count goes 42 → 63, so the support spacing matters far more than any area rule. Buy chairs by height first — a 1 in chair and a 3 in chair are different products, and the height is what sets the cover. The rebar chair page works the height, the tier gap and this count in full.

Chair count on a 480 square foot slab: a 4 ft support grid gives 42 chairs, a 3 ft grid 63, and the flat one-per-4-sq-ft rule 120 Count grid points, not square feet Same 480 sq ft slab, three ways of counting chairs 4 ft grid — 7 × 6 42 chairs 3 ft grid — 9 × 7 63 chairs flat rule — 1 per 4 sq ft 120 chairs  (×2.9 the grid) A tighter bar spacing does not by itself add chairs — one chair carries every bar that crosses it. What a tighter bar spacing adds is intersections to tie, not points to prop.
The chair count is a support-grid number, not an area rule. The flat one-per-4-sq-ft shortcut over-orders this slab by nearly three times, while moving the real support grid from 4 ft to 3 ft moves the count by half again. Buy chairs by height — the height sets the cover, and the count only decides how many of them.

Tie wire

intersections = bars across × bars along = 24 × 20 = 480 wire per tie × 480 ties × (1 + waste) ÷ 12 = linear feet 8 in × 480 × 1.10 ÷ 12 = 352 ft of wire 352 ft × 0.0104 lb/ft (16 ga annealed) = 3.66 lb → one 3.5 lb roll

The wire per tie depends on the knot, not the bar: a snap tie eats 4 to 6 in, a wrap and twist 6 to 9 in, a saddle tie 8 to 10 in, and a figure eight on heavy bars 10 to 14 in. Tie pattern matters more than anything else — tie every crossing and a 480 sq ft mat takes 480 ties; tie every other one and it takes 240, and the roll lasts twice as long.

What the three market leaders do. Omni, Procore and Raken calculate bars, length and weight — the same first half. None of them publishes the cover table, the chair-height conversion, a chair count or a tie-wire estimate. That is the whole gap this page fills.

The full takeoff, on one line each

ItemWorkingResult
Bars acrossfloor(286.5 ÷ 12) + 124
Bars alongfloor(238.5 ÷ 12) + 120
Net length(24 × 23.875) + (20 × 19.875)970.5 ft
Net weight970.5 × 0.668648.3 lb
Chair height3/4 in cover + 0.25 in (half of #4)1 in
Chairs(floor(24 ÷ 4) + 1) × (floor(20 ÷ 4) + 1)42
Intersections24 × 20480
Tie wire480 × 8 in × 1.10 ÷ 12 × 0.01043.66 lb
Order weight, 20 ft stock68 bars × 20 ft × 0.668908.5 lb
Order weight, 30 ft stock44 bars × 30 ft × 0.668882 lb

Swipe the table sideways for more columns →

The last two rows are the point every first-half calculator misses. The same 648.3 lb of steel is bought as 908.5 lb or 882 lb depending on which stock bar you order, because the offcut is a remainder, not a percentage. The estimator page works that arithmetic in full, and the slab page carries it through the lap splices.

Where clear cover meets development length

Cover does two jobs at once, and for the takeoff they pull in opposite directions. Push the bar in — bigger chairs, more cover — and the usable span shrinks, so the grid buys slightly less bar. Push it out and the grid grows. Development length does not enter that trade on this site, because the expression behind every number here has no cover term:

ld = [ fy ÷ ( C × λ × √f'c ) ] × ψt × ψe × ψg × db C = 25 for a #6 and smaller, 20 for a #7 and larger. Where the spacing and cover limits are not met the coefficient becomes 3/50 and 3/40, which is 1.5 times longer

fy, f'c, the bar diameter, the divisor C and three factors. Cover is not one of the factors, but it decides which C applies: the 19 in for a #4 and the 48 in for a #8 hold at 3/4 in of cover and at 3 in alike, and drop to 29 and 72 in the moment the cover falls below one bar diameter. That is the honest limit of any table: it answers one row exactly and leaves the rest to the clause. Above that limit, what cover moves is the grid. On our 24 ft × 20 ft slab, going from 3/4 in to 3 in of cover at the same spacing removes 16.5 ft of bar and 11 lb of steel — about 1.7 per cent of the 648.3 lb total, which is smaller than the difference between ordering 20 ft and 40 ft stock.

The development length page works the calculation for a #8 bar symbol by symbol and gives the tables for #3 to #11.

Watch: 44 bars, 42 chairs, one roll of wire

16-second walkthrough: 24 ft x 20 ft, #4 at 12 in on centre, 3/4 in cover — 24 + 20 bars, 970.5 ft, 648.3 lb net, a 1 in chair, 42 chairs on a 4 ft grid, 480 intersections and 3.66 lb of tie wire. From the rebarcount channel.

Common questions

How do I calculate how much rebar for a concrete slab?

Work the grid in clear distances: subtract the clear cover from both ends of each direction to get the usable span, divide by the centre-to-centre spacing, round down, and add one bar line. Multiply each direction's bar count by the bar length in that direction, and the total is the net length. For a 24 ft by 20 ft slab with #4 at 12 in o.c. and 3/4 in cover, that is 24 bars one way and 20 the other, 970.5 ft and 648.3 lb.

What clear cover does the calculator use?

None of its own — cover is a code value, not a choice. ACI 318-19 sets it: 3/4 in for interior slabs and walls with #11 bars and smaller, 1.5 in for interior beams and columns, 1.5 in for weather-exposed work with #5 bars and smaller, 2 in for weather-exposed work with #6 to #18 bars, and 3 in for concrete cast against and permanently in contact with earth. Use whichever line matches your exposure condition.

Does clear cover change how much rebar I need?

Yes, but only through the grid. More cover shortens each bar: going from 3/4 in to 3 in on our 24 ft by 20 ft slab removes 16.5 ft of bar and about 11 lb of steel, 1.7 per cent of the 648.3 lb total. Development length does not move with cover — the expression behind it has no cover term — so the lap splices inside that bar stay the length they were. The chair count does not change at all; only the chair height does.

How many rebar chairs do I need?

Count grid points, not area. A 480 sq ft slab on a 4 ft support grid is (24 ÷ 4) + 1 = 7 across and (20 ÷ 4) + 1 = 6 along, so 42 chairs; tighten the grid to 3 ft and it becomes 9 × 7 = 63. The per-area rule of one chair per 4 sq ft gives 120 on the same slab, nearly three times too many, because it treats a chair as supporting a point rather than a patch. Chairs come in fixed heights, so match the height to the cover table first and the count second.

How much tie wire do I need per intersection?

4 to 6 in for a snap tie, 6 to 9 in for a wrap and twist, 8 to 10 in for a saddle tie, and 10 to 14 in for a figure eight on heavy bars. At 8 in per tie with 10 per cent waste, each intersection uses about 0.0076 lb of 16 gauge black annealed wire — so a 480-intersection mat needs 3.66 lb, and a 3.5 lb roll covers it with a little to spare.

Do I have to tie every rebar intersection?

No, and on a crack-control mat on grade you normally should not. Tie every crossing around the perimeter and at the lap splices, then about half the interior crossings in a staggered pattern. Structural reinforcement, walls, columns and seismic work are tied fully. Tie wire holds the bars in position during the pour; it adds nothing to the finished slab's strength.

What is the difference between net weight and order weight?

Net weight is the steel in the finished grid — 648.3 lb on our slab. Order weight is what you buy, because bars come in fixed lengths and the offcut is a remainder, not a percentage. On 20 ft stock the job takes 68 bars, or 908.5 lb; on 30 ft stock it takes 44 bars, or 882 lb. Same slab, two order weights, and the heavier one leaves you with more cut ends to handle.

How much tie wire per ton of rebar?

Budget 7 to 12 kg of 16 gauge black annealed wire per tonne of steel, taking the top of that range for small bars and dense mats and the bottom for heavy bars and light tying. Our 480 sq ft slab is the low end of that: 3.66 lb of wire against 648.3 lb of steel is 5.6 kg per tonne, because only the perimeter, the laps and about half the interior crossings are tied. Carry the rate to a bigger job and a 20 tonne slab lands between 310 and 530 lb of wire, which at 0.0104 lb/ft is 30,000 to 51,000 ft, or 85 to 145 of the 3.5 lb rolls. The wire never scales with the steel alone — it scales with the intersections, which is why the rate has a range and not a number.

What this page does not do

It does not design the slab. Bar size, spacing, cover, the number of mats, laps and development lengths all come from the structural drawings and the engineer. This page takes those values and finishes the material takeoff so the accessory order and the weight are right. Cover values follow ACI 318-19 as published; some jurisdictions are on earlier editions, and the drawings and your engineer govern. Where the project specifies a cover different from the code minimum, use the project value.